Legislation Details

File #: 14-079    Version: 1 Name: Westgate Soundwall Repair - Accept
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 4/7/2014 Final action: 4/7/2014
Enactment date: Enactment #:
Title: Staff Report for a Resolution Accepting the Work for the Westgate Soundwall Repair Project, Project No. 2012.0200
Sponsors: Uchenna Udemezue
Related files: 14-081

Title

Staff Report for a Resolution Accepting the Work for the Westgate Soundwall Repair Project, Project No. 2012.0200

 

Staffreport

SUMMARY AND RECOMMENDATIONS

 

Staff recommends the City Council accept the work by Pleasanton Engineering Contractors, Inc., release the performance and payment bonds after the applicable statute of limitations expires, file the Notice of Completion and release the maintenance bond upon completion of the one-year maintenance period to the satisfaction of the Engineering and Transportation Director.

 

BACKGROUND

 

In April 2011 and again in May 2011, the Police Department reported incidents involving automobile collisions into the soundwall along the east side of Westgate Parkway.  The two separate collisions were both single vehicle collisions with the wall at approximately the same location, causing noticeable distress to the wall structure.

 

The soundwall separates Westgate Parkway from the backyards of residential properties along Timothy Drive and Marybelle Avenue.  The wall was constructed when the property was a privately owned industrial site and became the City’s responsibility when the right of way was acquired in 1987.

 

The project demolished and replaced the distressed section of soundwall.  The replaced section meets current Building Code regulations.

 

Analysis

 

On September 6, 2013, Pleasanton Engineering Contractors, Inc. was awarded the construction contract.  Construction began on November 8, 2013.  The completed work was inspected and found in accordance with the project specifications and City standards.

 

Previous Actions

 

                     On September 6, 2013, by Resolution No. 2013-117, the City Council awarded the construction contract to Pleasanton Engineering Contractors, Inc. for the subject project

                     On July 1, 2013, by Resolution No. 2013-098, the City Council approved the plans and specifications and called for bids for the subject project

 

Permits and/or Variances Granted

 

A City Building Permit was issued.

 

Fiscal Impacts

 

The total project cost is $70,000.  The construction cost of this contract was as follows;

 

Original Contract                     $37,000

Contract Change Orders                              $0

Total Contract Amount                     $37,000

 

The project cost is reimbursable through a combination of the vehicle owner’s automobile insurance and the City’s self-insurance.

 

Budget Authority

 

                     The improvements were funded using General Fund Capital Improvement project account No. 210-38-346

                     $50,000 was appropriated by mid-year adjustment per a memo signed by the City Manager dated May 8, 2012 

                     An additional $25,000 was loaned from existing General Fund Capital Improvement project accounts, to be reimbursed from insurance sources, when received

 

PREPARED BY:  John O’Driscoll, Associate Engineer, Engineering and Transportation Department