Legislation Details

File #: 14-272    Version: 1 Name: Fiber Broadband Network - AWARD (SR)
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 7/7/2014 Final action: 7/7/2014
Enactment date: Enactment #:
Title: Staff Report for a Resolution Awarding a Construction Contract to Flatiron Electric Group, Inc. for the Fiber Conduit for Broadband Network Project, Project No. 2013.0320
Sponsors: Uchenna Udemezue
Attachments: 1. Fiber Conduit Bid Summary
Related files: 14-273

Title

Staff Report for a Resolution Awarding a Construction Contract to Flatiron Electric Group, Inc. for the Fiber Conduit for Broadband Network Project, Project No. 2013.0320

 

Staffreport

SUMMARY AND RECOMMENDATIONS

 

The subject project will install conduit and pull boxes ready for the insertion of fiber optic communication cable. 

 

Staff recommends that the City Council award the contract to the lowest responsible bidder, Flatiron Electric Group, Inc., in the amount of $1,325,350.00 for the subject project.

 

BACKGROUND

 

In partnership with Lit San Leandro and to promote business growth in the local area, the City desires to expand its high speed communication infrastructure into underserved industrial areas of the City.  The City applied for and acquired grant funding from the United States Economic Development Agency (EDA) for installation of communications conduit.  The project will expand the City’s communications network capability by installing approximately seven miles of conduit ready to receive fiber optic cable.

 

The project included, as a base bid, the installation of a single two (2) inch diameter conduit. During the design process, an alternative installation of three 1-1/4 inch diameter conduits was considered. This alternative had advantages over the single conduit if additional fiber optic cable installations were desired in the future. Solicitations for bids included requests for both conduit options. The base bid option was designated as the method for determining the order of bids.

 

Analysis

 

The bids were opened on June 24, 2014.  Six (6) bids were received ranging from $1,258,262 to $3,669,080 for the base bid option. Flatiron Electric Group, Inc. (Flatiron) was determined by staff to be the lowest responsible bidder.  Flatiron’s proposal for the optional conduit was $67,088. Flatiron’s total construction cost of $1,325,350 is within the engineer's estimate for all work of $1,740,465.  Staff therefore recommends the inclusion of the alternate conduit in the project.

 

Staff verified that the contractor has a valid license with the Contractor’s State License Board.

 

Environmental Review

 

The project has been determined categorically exempt from CEQA per section 15304(f) Minor Alteration to Land.

 

Permits and/or Variances Granted

 

Caltrans issued an Encroachment permit for the segment of work within the State right of way.

 

Union Pacific issued seven individual Wireline Crossing Agreements for the locations where the project crosses railroad right of way.

 

Fiscal Impacts

 

The total cost of this project including design, permits, construction, contingencies and construction management is estimated at $2,300,000.

 

Budget Authority

 

The total appropriation for the Project is funded from the following sources:

 

EDA Grant                     150-38-347                     $2,121,000

Developer Fees for Street Improvements (DFSI)                     120-38-347                     150,000

Capital Improvement Project Fund                     210-38-347                          352,000

Total                                          $2,623,000

 

Through June 25, 2014 $171,000 has been expended with the remaining balance of $2,452,000.

 

ATTACHMENTS

 

                     Bid Summary

 

PREPARED BY:  John O’Driscoll, Associate Engineer, Engineering and Transportation Department