Legislation Details

File #: 14-509    Version: 1 Name: Monarch Bay Drive Bridge Maintenance and Repair ACCEPT (SR)
Type: Staff Report Status: Filed
In control: City Council
Meeting Date: 12/15/2014 Final action: 12/15/2014
Enactment date: Enactment #:
Title: Staff Report for a Resolution Accepting the Work for the Monarch Bay Drive Bridge Maintenance and Repair Project, Project No. 12-150-38-324
Sponsors: Uchenna Udemezue
Related files: 14-507

Title

Staff Report for a Resolution Accepting the Work for the Monarch Bay Drive Bridge Maintenance and Repair Project, Project No. 12-150-38-324

 

Staffreport

SUMMARY AND RECOMMENDATIONS

 

Staff recommends acceptance of the work by Vortex Marine Construction, Inc., filing of the Notice of Completion, release of the performance and payment bonds, and release of the maintenance bond upon completion of the one year maintenance period.

 

BACKGROUND

 

The City owns and maintains several bridges, some of which are periodically inspected by Caltrans.  Recent inspection reports for the bridge that carries Monarch Bay Drive over the Estudillo Canal (located immediately south of Marina Park) indicate that some of the concrete is damaged and that the bank at the northern abutment has eroded to the point that the abutment foundations are exposed.

 

The project repaired damaged concrete on the underside of the bridge, rebuilt the embankment at the northern end of bridge, and sealed the bridge deck.

 

Analysis

 

This project installed the above described improvements.  The work was performed in compliance with the contract documents and is now complete.

 

Current Agency Policies

 

Maintain and enhance the City’s infrastructure.

 

Previous Actions

 

On January 21, 2014, by Resolution No. 2014-006, the City Council awarded a contract for construction of the work to Vortex Marine Construction, Inc.

 

Applicable General Plan Policies

 

Policy 52.07: Ensure that sufficient funding is provided for the ongoing maintenance of City-owned facilities, including streets, street lights, traffic signals, landscaping, street trees, storm drains, public buildings, and other infrastructure.

 

Permits and/or Variances Granted

 

This work was done under the following permits and/or approvals:

                     U.S. Army Corps of Engineers Permit

                     San Francisco Bay Conservation and Development Commission Permit

                     California Department of Fish and Wildlife Authorization

                     San Francisco Bay Area Regional Water Board Certification

                     Alameda County Flood Control Permit

 

Environmental Review

 

This project is categorically exempt from CEQA per section 15302(c): Replacement or reconstruction of existing utility systems and/or facilities involving negligible or no expansion of capacity.

 

Fiscal Impacts

 

The total cost of this project is $315,000.  A summary of the cost of the construction contract with Vortex Marine Construction, Inc. is tabulated below.

 

Original Contract:                     $243,600

Change Orders:                     $    1,369

Total Contract Amount:                     $244,969

 

Budget Authority

 

This project was funded by Measure B Streets & Roads funds in account 144-38-324, authorized in the City’s FY11-12 Adopted Budget, and a federal grant under the Bridge Maintenance and Repair Program in account 150-38-324, which was appropriated with the contract award.

 

PREPARED BY:  Nick Thom, Senior Engineer, Engineering and Transportation Department